Apparent power
S = P / pf
- P = the connected load (kW)
- pf = the power factor (0.8 as a rule)
The distribution transformer sized from the connected load and the voltages, then placed on the board and the single line.
The rating steps and the loading basis.
S = P / pf
S(rated) = S × (1 + spare), rounded up to the next standard kVA
For reference. MO.tool works these out to help your design; the engineer remains responsible for it. Always check the edition of each standard your project uses and the requirements of the local authority (DEWA, ADDC, Civil Defence…).